I’m trying to model construction stages using result combinations and structural modifications. I encountered the following problem:
If I model the connection using rigid links, the model becomes unstable as soon as I deactivate the concrete slab in fields 2 and 3. However, if I model the connection using rigid beams, everything works fine.
Am I doing something wrong?
Attached is the model where the problem occurs.